The purpose of the level pricing grid is to preview to the user exactly what the future level pricing of the item will look like in the inventory file after the future prices are updated. In fact, the level pricing grid operates in a similar fashion to the one used on the cost/price tab of inventory maintenance. Users can modify the percentage over cost value or the dollar over cost amount directly in the grid. Also, users can change a price level from percentage over cost to a dollar amount over cost and vice versa.

 

Modify a percentage over cost value

A percentage over cost value can be identified as having values in both the Unit Price column and the % Over Cost column.

 

1.Double-click the desired percentage value to change in the % Over Cost column.
2.Enter the new percentage value and press the Enter key.

 

Modify a dollar amount over cost value

A dollar amount over cost value can be identified as a level price with a blank value in the % Over Cost column.

 

1.Double click the desired unit price to change in the Unit Price column.
2.Enter the new unit price for the level and press the Enter key. entrée will automatically calculate the dollar amount over cost, but it will not be visible to the user.

 

Changing a percentage based price level to a dollar over cost price level

1.Double click the unit price of the desired price level to change in the Unit Price column.
2.Enter the new unit price for the level and press the Enter key. entrée will then clear the value of the % Over Cost column and calculate the dollar amount over cost, but it will not be visible to the user.

 

Changing a dollar over cost price level to a percentage based price level

1.Double click the blank edit area of the desired price level to change in the % Over Cost column.
2.Enter the desired percentage markup for the price level and press the Enter key. entrée will automatically calculate the unit price based on the percentage value entered.

 

 

 

The level pricing grid will not be displayed when using the "wildcard" update option of the Cost/Price Update Method dialog.